Update #6

:white_check_mark: Milestone 1 complete :white_check_mark: (Design & Storyboard)

  • We achieved 100% completion on Saturday Aug 16th, :white_check_mark: 4 days ahead of schedule. :white_check_mark:
  • The contract with the Sandbox Foundation hasn’t been signed yet
  • Applied for milestone release payment of Milestone 1

Milestone 2 in progress - Prototyping

  • Prototyping was 65% complete last update, it is now 75% complete

  • Completed Learn Areas A, B, and C. Upcoming is Learn Area D, E, F, and the Big Game parkour race

  • We anticipate meeting the Sep 4th due date ahead of schedule.

Milestone 3 in progress - Voxel Art

  • Voxel Art was 20% complete last update, it is now 45%

  • Completed Learn Areas A, and B. Upcoming is Learn Area C, D, E, F, and the Big Game parkour race

  • We anticipate meeting the Sep 12th due date ahead of schedule.

Milestone 4 in progress - Integrate Everything

  • We have started integrating the prototyping, voxel art, and refinement. It is 20% complete.

  • Completed Learn Areas A. Upcoming is Learn Area B, C, D, E, F, and the Big Game parkour race

  • We anticipate meeting the Sep 27th due date ahead of schedule.

We are still ahead of schedule.

  • Here is Learn Area B: What the Sandbox DAO structure is and how it works

SIP-32 Update History
4 Likes