Update #7
Milestone 1 complete
(Design & Storyboard)
- We achieved 100% completion on Saturday Aug 16th,
4 days ahead of schedule. 
- The contract with the Sandbox Foundation hasn’t been signed yet, awaiting Foundation signature
- Applied for milestone release payment of Milestone 1
Milestone 2 in progress
Prototyping
- Prototyping was 75% complete last update, it is now 100% complete

- The contract with the Sandbox Foundation hasn’t been signed yet, awaiting Foundation signature
- Applied for milestone release payment of Milestone 1
Milestone 3 in progress - Voxel Art
- Voxel Art was 45% complete last update, it remains 45%
- Completed Learn Areas A, and B. Upcoming is Learn Area C, D, E, F, and the Big Game parkour race
- We anticipate meeting the Sep 12th on schedule.
Milestone 4 in progress - Integrate Everything
- We have started integrating the prototyping, voxel art, and refinement. It is 20% complete.
- Completed Learn Areas A. Upcoming is Learn Area B, C, D, E, F, and the Big Game parkour race
- We anticipate meeting the Sep 27th due date ahead of schedule.
Milestone 5 in progress - Internal Test
- We started internal testing alongside integration of GM and Voxel art, completed Learn Area A testing and win condition test.
- We are 20% complete.
We are on schedule.
SIP-32 Update History
4 Likes