SIP-32: DAO Educational Experience in the Sandbox - RFP Selection

Update #8

SIP-32 contract signed with DAO Admin Team, milestones were simplified, combining the 7 on our original RFP down to 4, and I had to recalculate some of the progress percentages.

:white_check_mark: Milestone 1 completed 100% :white_check_mark:

  • Design & Storyboard
    • Finalize the gameplay loop, design of the learning areas, dialogue tree, quest tree, and provide a visual storyboard of the whole experience.
  • Completed on Aug 16th, 4 days ahead of schedule

:white_check_mark: Milestone 2 completed 100% :white_check_mark:

  • Working Prototype
    • Build the experience in Game Maker with placeholders, be able to trigger the win condition after completing all quests.
  • Completed on Sep 4th, 1 day behind schedule

Milestone 3 in progress 22%

  • Internal Test & Quality Check
    • 50% complete finishing all voxel assets
    • 30% complete fully integrating all assets into the experience
    • 10% complete conducting internal test
    • 0% complete fixing requested changes by the DAO Admin Team
  • Due Oct 1st

Milestone 4 not started

  • Community Playtest & Final Delivery
    • 0% complete conducting Community Playtest. Looking to schedule it the week of Oct 6th.
    • 0% complete delivering the full experience
  • Due Oct 29th

SIP-32 Update History
2 Likes